"Three, two, one, fire!" With the countdown, Changan Yiyang Power Generation Co., Ltd. phase III 2×1 million kW expansion and upgrading project, unit 5 boiler ignition success, marking the unit officially entered the trial operation stage, laid a solid foundation for grid-connected power generation, the unit put into operation is a milestone.

Unit 5 of the boiler ignition is the first million units of Shaanxi Coal Group, and it is also the first million units of Changan Yiyang Company to start construction. Since Unit 5 poured the first tank of concrete on March 27, 2023, and fully started construction, 15 major participating units, more than 4,500 construction personnel, more than 640 days of continuous cooperation, day and night work, according to the project progress node, efficient and high-quality compression, Unit 5 officially entered the full set of start-up and commissioning stage. A key step has been taken towards the goal of grid-connected power generation.